Lagos Water Corporation’s rehabilitation drive goals to revive waterworks, entice funding, enhance effectivity and strengthen local weather resilience amid rising demand and infrastructure challenges, writes Sunday Ehigiator
Dike Onwuamaeze
The Lagos Water Corporation (LWC) below the management of its Managing Director, Engr. Mukhtaar Tijani, lately obtained worldwide recognition in Glasgow below the 2026 International Water Association (IWA) Climate Smart Utilities Recognition Programme. The honour made the LWC the second Nigerian utility to obtain the popularity after Kaduna in 2022, and the primary in southern Nigeria. The programme assesses utilities on local weather adaptation, greenhouse-gas mitigation and climate-smart management. The recognition additionally highlights LWC’s efforts to construct resilience regardless of longstanding funding and operational challenges.
The Glasgow recognition got here towards the backdrop of a broader effort to revive dormant waterworks, rehabilitate crucial infrastructure, modernise distribution networks and strengthen the Corporation’s operations, as Lagos seeks to construct a water system able to responding not solely to immediately’s calls for but in addition to the rising pressures of urbanisation and local weather change. That actuality offered a formidable problem when Tijani assumed workplace as Managing Director of the Corporation in July 2023, alongside Engr. Helen Omolanke Taiwo as Executive Director, Operations.
At the time, the Corporation reported that solely two of its 4 main remedy crops have been purposeful, producing a mixed 15 million gallons of water day by day, whereas solely six of its 48 mini and micro waterworks have been working, and even these have been under their capacities.
Three years later, the image has modified to one in every of an establishment present process a broad-based programme of rehabilitation, restructuring, technological modernisation, and partnership constructing.
For Tijani, nonetheless, the duty seems to have been much less about recognition and extra about rebuilding the establishment from its foundations, with main interventions now targeted on restoring manufacturing capability and bettering the reliability of the programs required to transfer water throughout Lagos.
Replacing crucial pumping gear
One of the newest interventions was the substitute of crucial pumping gear at Iju Waterworks after greater than three a long time of service. LWC has obtained six clear-water pumps with motors and one further pump head for Iju Waterworks, in addition to two raw-water pumps with motors and management programs for the Adiyan Intake. Installation of the brand new gear at Iju is ongoing.
With Governor Babajide Sanwo-Olu’s imaginative and prescient to advance funding in crucial water infrastructure, the intervention is predicted to enhance water manufacturing and operational reliability at Iju after the brand new gear is put in and commissioned.
Powering the waterworks
Mukhtaar Tijani’s engineering and energy-sector expertise has introduced a beneficial perspective to his management of the water sector. Reliable electrical energy is crucial to remedy crops, pumping stations and distribution networks. That understanding is mirrored within the collaboration between LWC and the Ministry of Energy and Mineral Resources, linking the rehabilitation of water infrastructure with the ability programs required to preserve it operating. Another main part of the infrastructure programme is the rebuilding of the Akute Independent Power Plant, which is meant to present devoted energy to crucial water infrastructure.
On April 26, 2026, Governor Sanwo-Olu presided over the signing of the ability settlement with Fenchurch. Rebuilding of the 26 MW plant started on September 26, 2026, with the prevailing engines being eliminated for substitute with new fuel engines. The plant is deliberate to provide Akute Intake, Iju and Adiyan waterworks.
Financed by Zenith Bank below the state’s Public-Private Partnership (PPP) scheme, the reported implementation plan is to ship 10 MW inside 4 months and the remaining 16 MW inside 12 months.
The dedicated-power funding is predicted to deal with one of many crucial constraints affecting water manufacturing and pumping reliability, significantly because the Corporation advances the rehabilitation of main waterworks and the completion of Adiyan II.
The Audacious Mandate
One of the defining options of Mukhtaar Tijani’s tenure has been the choice to method the Corporation’s challenges as interconnected issues somewhat than remoted failures.
Production can’t be separated from pumping capability. Pumping can’t be separated from dependable energy. Increased manufacturing is of restricted worth with out purposeful distribution networks.
The cancellation of funding for the USAID-supported Lagos Urban Water, Sanitation and Hygiene (LUWASH) programme, initially valued at roughly $45 million, compelled the Corporation to assessment its plans. The disruption adopted President Donald Trump’s halt to overseas help and the next withdrawal of USAID help.
LWC had constructed its four-year rehabilitation plan across the anticipated funding. With no preliminary price range provision to cowl the ensuing hole, Mukhtaar Tijani and the Corporation reassessed their priorities, choosing waterworks that the Lagos State Government might fund. The response was to preserve rehabilitation shifting, despite the fact that the total programme might not proceed as initially deliberate.
That philosophy is mirrored in Mukhtaar Tijani’s public statements. During a latest inspection, he stated: “The work is progressing steadily,” including that “We are pleased with the progress we have made so far. Procurement has been completed, all the equipment has been delivered to the site, and installation is progressing as scheduled.”
Reviving Dormant Waterworks
Among probably the most seen points of the programme has been the rehabilitation and recommissioning of services that had both develop into dormant or have been working under potential.
The Mosan Okunola Waterworks was recommissioned on December 14, 2023, with reported manufacturing restored to two million gallons day by day. Supply was additionally prolonged into Baruwa, an space that had confronted extended water shortage and groundwater contamination.
The intervention is important not merely due to the restoration, however as a result of the Corporation moved past manufacturing to join the water to communities, with further connections and community extensions deliberate.
Akilo Waterworks was recommissioned on December 12, 2025, following the rehabilitation carried out with WaterHelp Nigeria and Armani Beauty’s Aqua for Life initiative. The facility has a capability of 4,500 cubic metres day by day, with the capability to serve roughly 100,000 residents, alongside 20 water kiosks. The venture included new boreholes, substitute of electromechanical gear and rehabilitation of the distribution community. Importantly, the partnership additionally included family enumeration, baseline surveys, hygiene promotion and group engagement.
This mixture of bodily infrastructure and group engagement illustrates an rising mannequin throughout the Corporation: water tasks are more and more being thought of not merely as engineering assignments, however as service-delivery programs.
The rehabilitation programme additionally contains the development of a brand new mini waterworks on Lagos Island and the rehabilitation of Ajegunle Waterworks.
Alongside these interventions is the $2.5 million grant-backed rehabilitation of Ojokoro Waterworks, supported by WaterHelp Nigeria and GroupWater, with the involvement of common YouTuber MrBeast. The partnership displays the worldwide help being drawn to the Corporation’s infrastructure programme below Mukhtaar Tijani’s management.
The Ojokoro rehabilitation contract was signed on September 4, 2026, with Bayroyal International Ltd. It contains civil, mechanical, electrical and instrumentation upgrades, borehole rehabilitation and drilling, photo voltaic integration, stress monitoring, leakage detection, automated community administration, metering and community growth. It is predicted to profit roughly 72,000 residents when delivered. The Lagos Island, Ajegunle and Ojokoro tasks are focused for completion inside 12 months.
Adiyan II: Moving a long-delayed venture ahead
Perhaps probably the most consequential venture within the Corporation’s rehabilitation programme is Adiyan II.
The long-delayed waterworks venture was revived in November 2023 following renewed authorities funding commitments, contractor remobilisation and stronger venture oversight. Governor Babajide Sanwo-Olu inspected the Adiyan II venture in February and December 2025 as work progressed, offering help to the venture alongside the venture oversight being undertaken by Mukhtaar Tijani and the Corporation’s administration.
Governor Babajide Sanwo-Olu publicly acknowledged Mukhtaar Tijani’s function in reviving Adiyan II on the first Lagos Physical Planning Summit, held at Eko Hotels and Suites, Victoria Island, on October 15–16, 2024.
Following former Governor Babatunde Fashola’s attraction to prioritise the venture, Sanwo-Olu recommended Mukhtaar Tijani’s persistence and constant advocacy in bringing the long-stalled waterworks again on observe.
When accomplished, Adiyan II is designed to produce 320,000 cubic metres of handled water day by day, greater than 70 million gallons, and is projected to serve greater than 5 million residents. Tijani has repeatedly highlighted the significance of the venture. In a public replace, he stated he had mentioned the Adiyan II venture and the Corporation’s broader infrastructure upgrades, together with the event of community intelligence to enhance water distribution.
The venture, which is predicted to be operational in 2027, can be being pursued alongside funding in devoted energy infrastructure, together with the rebuilding of the Akute Independent Power Plant, which is deliberate to provide Adiyan in addition to Iju and Akute Intake.
Rebuilding Network Beneath the sleepless metropolis
Water infrastructure will not be solely about remedy crops. Much of the problem lies beneath the roads and communities via which water should journey.
Under Mukhtaar Tijani’s management, the Corporation has labored with technical companions to hint and digitise greater than 170 kilometres of transmission pipelines utilizing Geographic Information System know-how.
Previously unmapped sections have been included, whereas valves, junctions and key clients have been geotagged. A preliminary hydraulic mannequin was additionally developed to analyse water flows and stress.
In 2025, LWC went additional by deploying a robotic pipeline inspection machine developed with Konsadem Associates and McAlpha Inc. The know-how is designed to determine corrosion, cracks, blockages and potential leak factors. The ensuing data has been used to inform rehabilitation priorities in areas together with Ishasi, Apapa, Magodo, Alexander and Isolo.
The significance of this intervention is that it strikes infrastructure administration from guesswork in direction of data-driven decision-making.
Opening the PPP door
Another part of the technique is the Corporation’s try to leverage non-public capital and experience with out surrendering authorities possession of its water belongings.
LWC developed its 2025–2030 Strategic Business Plan, unveiled in December 2024, with 12 precedence targets and a costed implementation schedule.
The priorities embrace rehabilitation of main remedy crops and trunk mains, completion of Adiyan II, restoration of energy infrastructure, rehabilitation of 16 mini and micro waterworks, workers improvement and improved buyer engagement.
The Corporation additionally established a public-private partnership framework for seven pilot schemes masking Lekki, Akilo, Victoria Island Annex, Magodo, Abesan, Alexander and Apapa. Following stakeholder engagement in August 2025, formal invites for bids have been issued.
The proposed mannequin retains authorities possession of the belongings whereas introducing non-public financing and operational experience.
At a workers engagement on the proposed PPP programme, Mukhtaar Tijani articulated his ambition succinctly: “My vision is to see the waterworks alive.” He additionally spoke of the target of enabling residents to expertise functioning water provide of their communities.
Building for the longer term
The Corporation’s present route more and more extends past repairing what’s damaged to making ready for future calls for. That contains climate-smart infrastructure, improved community intelligence, digital buyer programs, stronger partnerships and new financing fashions.
As Lagos State’s inhabitants grows, the water demand continues to enhance, making it mandatory to broaden infrastructure to preserve tempo. In response, the Corporation is growing a grasp plan to information its efforts to shut the hole between water provide and demand.
The plan is being designed as a roadmap masking the quick time period, from 2026 to 2030; the medium time period, from 2031 to 2040; and the long run, from 2041 onwards.
Through this method, the Corporation goals to place present rehabilitation efforts inside a wider plan for assembly the state’s future water wants, linking the restoration of present services with the infrastructure growth required to serve a rising inhabitants.
From restoration to resilience
Perhaps probably the most revealing measure of Mukhtaar Tijani’s work is the breadth of the agenda. The goal is not merely to restore particular person waterworks. It is to create a utility able to producing, distributing, metering, and managing water extra effectively, whereas attracting technical experience and funding.
The Corporation’s partnerships involving WaterHelp, JICA, the Resilient Water Accelerator, Suez and different technical and funding companions proceed to present a part of the institutional backing for the reforms. Yet, the final word measure of any water utility stays simple: whether or not residents can activate a faucet and obtain protected, dependable water.
That is why the importance of the reforms at Lagos Water Corporation lies not solely within the variety of tasks introduced or services rehabilitated, however within the try to reconnect infrastructure funding with on a regular basis service supply.
The journey will not be full. Some tasks stay below development, some advantages are nonetheless projected, and several other infrastructure investments are at procurement or implementation levels. But the report since 2023 reveals an establishment pursuing change on a number of fronts, from dormant waterworks and ageing pumps to digital mapping, workers restructuring, private-sector partnerships and local weather resilience.
For a metropolis that doesn’t sleep, whose inhabitants and water demand proceed to broaden, that institutional rebuilding might finally show as necessary as any single waterworks. The job forward is to flip the momentum into sustained, measurable and reliable water provide for extra Lagos residents.
As Tijani places it, the ambition is easy: to carry the waterworks again to life and be sure that the Corporation’s transformation finally interprets into dependable water provide for the individuals it was established to serve.